The deadline that matters is not the headline year. It is the application date in your delegated act. Under the ESPR, Regulation (EU) 2024/1781, almost every Digital Product Passport duty arrives in two steps: the framework Regulation first, then a delegated act for your product group. Between those steps sit adoption, scrutiny, publication and entry into force — and then, by law, a minimum wait. Article 4(4) is the rule that turns a headline into a calendar: the date of application of a delegated act shall not be earlier than 18 months from its entry into force.

The 18-month rule, in the text

Article 4 empowers the Commission to adopt delegated acts setting ecodesign requirements for a product group — the acts that specify, among the elements listed in Article 8, whether a passport is required, at what granularity, and with which data. Article 4(4) then disciplines the timing in two sentences. First, the Commission shall provide economic operators with sufficient time to comply, particularly taking into consideration the needs of SMEs, in particular microenterprises. Second, the floor: application not earlier than 18 months from entry into force — except in duly justified cases, for the whole act or for some specific requirements, or in cases of partial repeal or amendment of a delegated act, where an earlier date may be set. Eighteen months is therefore a minimum, not a fixed offset: an act may give more time, but not normally less.

Four dates, four different events

Most confusion comes from treating four distinct events as one. Separate them and every ESPR timeline becomes readable:

DateWhat it isLegal weight
Working Plan yearThe year in the Commission’s Working Plan 2025–2030 (COM(2025) 187, 16 April 2025) for the expected adoption of your group’s act: iron & steel 2026; textiles, tyres and aluminium 2027; furniture 2028; mattresses 2029.Indicative only — a planning signal, not law.
AdoptionThe Commission adopts the delegated act and notifies it to the European Parliament and the Council (Article 72(5)).The text is fixed, but it is not yet in force.
Entry into forceUnder Article 72(6), the act enters into force only if neither Parliament nor Council objects within two months of notification — a period extendable by two more months — and after publication in the Official Journal, on the date the act itself specifies.The 18-month clock starts here, not at adoption.
ApplicationThe date from which products placed on the market must comply, set in the delegated act itself.Your deadline. Normally at least 18 months after entry into force.

Worked examples — arithmetic, not promises

Apply the rule to the Working Plan years and the picture shifts by roughly two years. These are illustrations of the arithmetic, not fixed dates — the real application date will be the one printed in each act:

  • Iron & steel (adoption indicatively 2026): add the scrutiny and publication interval, then at least 18 months — the earliest normal application falls in 2028, not 2026.
  • Textiles, tyres, aluminium (adoption indicatively 2027): the same arithmetic points to application around 2029.
  • Furniture (2028) and mattresses (2029): application moves into 2030 and beyond on the same basis.

Working Plan years are indicative and can slip — and if adoption slips, application slips with it. The same floor technique appears in Article 4(7): the first delegated act could not enter into force before 19 July 2025.

The exception that proves the reading

Batteries look different because they are different. The battery passport duty — 18 February 2027 for electric-vehicle, light-transport and larger industrial batteries — is written directly into Article 77 of Regulation (EU) 2023/1542, a sector Regulation with its own fixed date. No ESPR delegated act, no 18-month computation. When a date is fixed in the parent law, it binds as printed; when a date must pass through a delegated act, the four-date method above is how you find it. Our ESPR timeline sets out the sequence of product groups, and the battery passport guide covers the fixed-date case.

A five-step method for any delegated act

  • Find your act, not your headline: identify the delegated act for your product group and read its final articles, where entry into force and application are set.
  • Separate the four dates: write down the Working Plan year, the adoption date, the entry-into-force date and the application date as four lines — never merge them.
  • Check for staged application: acts can apply different requirements at different dates, and Article 4(4) allows duly justified earlier dates for specific requirements — read requirement by requirement.
  • Work backwards from application: identifiers, supplier data, conformity assessment and labelling all have to be ready before the first product is placed on the market under the new rules, not on the day itself.
  • Use the transition for data, not for waiting: the 18 months are the legislator’s estimate of the work — composition, origin, recycled content and repair data live with suppliers, and collecting them is the long pole in every passport project.

How Ledger Consortium helps

Ledger Consortium aggregates the product data held by you and your suppliers, anchors each passport record on a governed blockchain — timestamped and tamper-evident — and manages the regulatory updates as delegated acts are adopted and begin to apply, so a change in the calendar does not become a rebuild of the system. Plainly, as always: anchoring proves a record existed and has not been altered; it does not certify that the data a client supplied was true — accuracy remains the responsibility of the operator placing the product on the market. Costs are predictable, with no token or crypto exposure, and the platform is GDPR- and eIDAS-aligned. In Italy, the Ledger DPP is distributed by Il Sole 24 Ore (Valore24), whose channel onboards dozens of companies per month. See a working passport in our live demo, browse News, and keep the full sequence in view with the ESPR and DPP timeline.